Ahead of Schedule. Then It Rained.

Last month we told you our DIGS project in Midtown Omaha was ahead of schedule. Then it rained. So here’s the update, the same way we give it to the owners: early, with the count.

“Wet, wet, wet”

That’s how our project manager opened the DIGS schedule review at the end of September. A weather day on Friday. Four to six inches of rain in the forecast for the week after.

DIGS is 188 apartments in two buildings, and at that point the whole job was waiting on its foundation walls. You can’t pour walls in the mud. Our team spent four or five days in September doing nothing but pumping water, so the next dry day could be a working day.

As of this week, DIGS has logged 10 weather days since Sept. 1. The floor planks on the north building are still set for the second week of November.

Drone close-up of the DIGS apartment foundations in Midtown Omaha after a week of rain
DIGS, Midtown Omaha, Oct. 1.

The part owners actually feel

If you own the building, you can’t do anything about the rain. You can plan around it, if you hear about it in time. Your lender, your leasing plan, and your move-in date all depend on that.

So every weather day goes on a list, and the list comes up at every owner meeting. Nobody finds out at the end of the job.

Why we’re telling this story

We develop, build, manage, and hold buildings too. We’ve sat in the owner’s chair, and we run our jobs the way we’d want to be treated in it. That goes for these stories too. When we tell you a project is ahead, we’ll tell you when it isn’t.

Build a better community through long-lasting relationships. That’s our purpose. Relationships last when the bad news shows up early.

Have a project where the schedule has to hold? Tell us about your project →

Want more stories like this? Get Sam’s monthly insights →

Previous